Monday 28 July 2014

Selamat Hari Raya Puasa



Today we took the time to prepare for the casting of the first storey slab. This floor houses the main reception, a Heritage Centre, Admissions, the Foundation office and Alumni, The High School office, University Advising and the Head of Campus offices along with a large social and gathering place for students and staff that will link into the tent plaza area. 

The area that we are about to construct.

One good reason to study mandarin - We have a wide variety of nationalities on the site ....The plan broken up into teams and hopefully clear to all....

Concrete "Elephant" pumps on site ready for tomorrow.


And finally just in case this blog gives the impression that everything always goes perfectly to plan..  This wasn't in the plan for the fire hydrant installation today.......



The conclusion....


After raining most of the morning - 4pm finally getting going on the casting,






Some of the 92 concrete trucks involved in this concrete pour...

02:45 - Finished! 622 m3 of Concrete formed into a building!